Two massive reactors for a weight of more than 1000 tons are installed on the site of Pavlodar Oil Chemical Refinery
페이지 정보
Writer GETech Date17-03-23 10:45 Hit263 comment0본문
In the first decade of December 2016, two reactors of diesel hydro treating each 550 tons were delivered and installed on
the site of Pavlodar Oil Chemistry Refinery.
This shipping operation is the first delivery in the history of independent Kazakhstan, performed and accomplished through
This shipping operation is the first delivery in the history of independent Kazakhstan, performed and accomplished through
the Northern Sea Route, the shortest path from Asia to Europe. The reactors overcame more than 15 thousands kilometers by
sea and 15 kilometers on the ground, to be able to accept them in the city of Pavlodar, a special temporary jetty in Michurino
settlement was built.
“Global Engineering Technology” ordered this unique equipment from South-Korean enterprise Hyundai Heavy Industries. It headed off to Kazakhstan from Mipo port in Ulsan city and was on track for approximately 2 months. For Koreans, delivery
“Global Engineering Technology” ordered this unique equipment from South-Korean enterprise Hyundai Heavy Industries. It headed off to Kazakhstan from Mipo port in Ulsan city and was on track for approximately 2 months. For Koreans, delivery
of such outsized shipment through the Northern Sea Route was performed for the first time ever, but now, after successful
cargo supply, usage of this route is planned to be frequent.